  Project Period
 
  2003.10.9 - 2004.6.22
 
  Project Overview
   
  Replacement of the MMI(Man-Machine Interface) system including server and operator stations of ABB
Procontrol P13/42 DCS for Bundang CCPP to new MMI system on the basis of ARIDES(Advanced Real-time
Information DEployment System) development platform
   
  Project Outcomes
 
  * Proofing of system reliability through more than one year stable operation
* Reduction of upgrade investment cost
* Improvement of expandability and maintainability of the system
* Increase of plant availablity
   
  The necessity of the business
   
  * The existing computer system for process control established by Korea South East Power Co. in the central control room of Combined Cycle Power Plant Bundang is a core facility that checks and operates the operation condition of the whole facility in running the power plant. It is ABB Procontrol P13/42 DCS, block #1 is a PRAUT system built in 1992 and block #2 is a PMS system built in 1997. But, it was necessary to improve the system due to the difficulties of repairs and maintenances, the deterioration of capacity and the limit of function, as the facility is getting aged. Thus, Korea South East Power Co. pushed ahead with the international bid and BNF Technology received an order in the competition with promising foreign venders based on the distinguished technique and price competition. The reduction of facility investment cost and the freedom from technology governance to autonomy through this business have a great ripple effect to the power plant business in general with the successful business performance.
   
  Specification of the system
   
 
Specification of the system
Technology specification
ABB Procontrol(PRAUT)
System structure
Limited server-client structure
server-client structure
Communication Interface PPS Dr. Seufert Interface Board G3 Interface Card
Control device Keyboard/ Hardwired Mouse/network
server BUL DPS 200 ftServer2.4 GHz Xeon
Operation system GECOS HVS6 Window 2003, XP
CPU capacity 4MB-8MB 1 GB
Hard disc capacity 300MB 73 GB
Past data storage capacity 5days limitless
Real time trend Period of scan - 2sec
Maximum span - 2 hour
Period of scan - 10 msec
Maximum span - limitless
Data backup
tape CD
Other operation function
N/A - Point Search
- Tag Detail Information
- Output Command Display
   
   
  Project Period
   
  2005.4.20 - 2005.12.20
   
  Project Overview
   
  Replacement of the OPS(Operator Interface system) including server and operator stations of MHI MIDAS-
8000 DCS for Buchun CHPP to new MMI system on the basis of BNF own ARIDES(Advanced Real-time
Information DEployment System) development platform
   
  Project Outcomes
   
  * Newly developed computer system will be applied step by step by 2006.
* Reduction of upgrade investment cost
* Adoption of a state of the Arts computer technologies
* Improvement of expandability and maintainability of the system following the use of the latest hardware
and operating system
* Customizing of various user requirements
   
  The necessity of the business
   
 

Computer system for process control built in 1992 in the central control room of GS Power Co. Bucheon combined heat and power plant was MIDAS-8000 of Japan¡¯s Mitsubishi Heavy Industries. It is the core facility that checks and operates the whole operation condition in running the power plant. But, as the system are getting aged, the initialization due to the malfunction of them were so frequent and the difficulty of repairing and maintaining due to the production stoppage of spare parts, especially due to the limit of the facility function, it is difficult to gain the operation data fit for the user¡¯s additional requirement. In solving this problem, it is possible to upgrade it to the latest version of Mitsubishi Heavy Industries with the excessive investment cost. Thus, we reviewed the technology in multi angles and we judged that we can upgrade it with our own technology. Then we started to develop new computerization system by using the BNF Technology developed ARIDES (Realtime Information DEployment System) development platform.

   
  Specification of the system
   
 
Specification of the system
Technology specification
ABB Procontrol(PRAUT)
System structure
Limited server-client structure
server-client structure
Communication Interface Ethernet + its own protocol Ethernet + TCP/IP
Control device Special Function Keyboard Standard Mouse/keyboard
server Fujitsu Astation-240 HP DL580 3.33 GHz Xeon
Operation system SA/X Unix Redhat AS v4 Linux
CPU capacity 16M 2 GB
Hard disc capacity 384MB 300 GB RAID
Past data storage capacity 30 days(180 point) limitless
Real time trend Period of scan - 10sec
Maximum span - 2 hour
Period of scan - 100 msec
Maximum span - limitless
Data backup
tape CD
Other operation function
  - Point Search/ Viewer
- Point Configurator
- X-Y Plot
- Composed Point Builder